Project Overview
RA Smith Contracting built the Upper South Creek brine pipeline for John Holland as a subcontractor on Sydney Water's Advanced Recycling Centre project. The $13 million package covered 14.3km of DN375 OPVC pipeline across rural and urban ground.
The pipeline carries brine, a byproduct of the recycling process, to its discharge points. The team also placed 69 appurtenances, built 25 cast in-situ scour bases, then tested and commissioned the line. Work like this is part of our water construction services.
Sydney Water's Upper South Creek program delivers wastewater infrastructure for the Western Sydney region.
Completed November 2024
The Challenge
The pipeline ran through farmland and built-up areas. On rural stretches, the crew worked with property owners on site access and livestock safety. In urban areas, council traffic requirements applied, and trenching in school zones and on major roads took place at night.
Sydney Water maintenance holes and pump scour chambers sat along the route. Working safely around them took a purpose-built barrier system.
Council and Sydney Water environmental requirements covered the whole alignment, including erosion, sediment and waterway protection.
The Solution
RA Smith worked with John Holland, Sydney Water, property owners and councils to line up access and approvals.
Access and livestock. Temporary fencing protected livestock and kept access open for property owners.
Night work. Trenching in school zones and on major roads took place at night.
Barrier system. RA Smith's Managing Director designed a barrier system for working safely around Sydney Water maintenance holes and pump scour chambers.
Environmental control. Erosion control, sediment management and waterway protection met council and Sydney Water requirements.
Project Outcome
RA Smith delivered, tested and commissioned the 14.3km brine pipeline to Sydney Water's specifications.
John Holland later re-engaged RA Smith on further projects. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.
Technical Scope
FAQs
RA Smith installed 14.3km of DN375 OPVC brine pipeline for John Holland on Sydney Water's Upper South Creek Advanced Recycling Centre project, then tested and commissioned it.
The pipeline has 69 appurtenances, including hydrants, air valves, jetting points and scours, plus 25 cast in-situ scour bases.
It carries brine, a byproduct of the recycling process, to designated discharge points.
RA Smith's Managing Director designed a barrier system for working safely around Sydney Water maintenance holes and pump scour chambers.
RA Smith worked as a subcontractor to John Holland on Sydney Water's Upper South Creek Advanced Recycling Centre project.