Project Overview
RA Smith Contracting built the Corrimal Coke Works sewer for Legacy Property, installing 520m of DN450 polypropylene gravity sewer at an average depth of 6.5m. The $2.7 million contract included realigning existing sewer infrastructure to Sydney Water's requirements.
The team also did the enabling works for future development of the former coke works site at Corrimal, near Wollongong. Construction took place from August 2024 to March 2025. Projects like this are part of our sewer construction services.
The confined site had strict controls on noise, lighting, sediment and heritage.
August 2024 – March 2025
The Challenge
The site is next to a Grey-Headed Flying Fox camp. The species is vulnerable, so the team had to keep noise, lighting and activities near the habitat under tight control.
Excavation and earthworks meant a constant risk of sediment runoff, especially in wet weather. The site also has areas of Aboriginal cultural significance. An Aboriginal Heritage Impact Permit (AHIP) is the legal approval needed before any work that could harm Aboriginal objects or places. Work in those areas had to align with the permit.
Planning, stakeholder consultation and full compliance were part of the Corrimal Coke Works sewer job from day one.
The Solution
Risk management came first, with stakeholders involved on compliance from the start.
Sediment control. Silt fences and sediment basins protected nearby waterways and habitat.
Flying fox protection. The team adjusted work schedules and kept noise and lighting under control within 75m of the camp.
Cultural heritage. We worked with stakeholders to meet the AHIP conditions and protected the identified heritage areas during construction.
Live sewer connections. The crew made concurrent connections into the live sewer under Sydney Water's Flow Isolation and Flow Management (FIFM) requirements, with detailed FIFM planning behind them. At CH 520, a bypass diverted the existing flows while the new inlet was built into the manhole.
Project Outcome
RA Smith delivered the gravity sewer and its enabling works at the Corrimal Coke Works site.
At Corrimal, RA Smith built the sewer and met its environmental and cultural heritage obligations on the same site. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.
Corrimal Coke Works Sewer Case Study
PDF · Full technical scope
Technical Scope
FAQs
RA Smith installed 520m of DN450 polypropylene gravity sewer for Legacy Property, with three DN1200 manholes, one DN1800 manhole and the enabling works for future development of the site.
The pipe averages 6.5m deep, and 218m of it is encased in concrete.
FIFM stands for Flow Isolation and Flow Management. At Corrimal, RA Smith made concurrent connections under these requirements and set up a bypass at CH 520 to divert the existing flows.
We adjusted work schedules and kept noise and lighting under control within 75m of the Grey-Headed Flying Fox camp.
The sewer had foundation, compaction, air, vacuum, CCTV and ovality testing to Sydney Water standards.