Corrimal Coke Works Sewer

Corrimal Coke Works Sewer

Greg Fulmer

|

April 9, 2025

Client

Legacy Property

Location

Corrimal, NSW

Value

$2.7 million

Completed

March 2025

Trench along the Corrimal Coke Works sewer alignment with an excavator working beyond.Trench along the Corrimal Coke Works sewer alignment with an excavator working beyond.
Crew setting up a tripod beside an existing manhole at Corrimal.Crew setting up a tripod beside an existing manhole at Corrimal.
RA Smith excavator on cleared ground at the Corrimal site.RA Smith excavator on cleared ground at the Corrimal site.
Pole and bushland beside the works area at Corrimal.Pole and bushland beside the works area at Corrimal.

Project Overview

Corrimal Coke Works sewer infrastructure in a highly sensitive environment

RA Smith Contracting built the Corrimal Coke Works sewer for Legacy Property, installing 520m of DN450 polypropylene gravity sewer at an average depth of 6.5m. The $2.7 million contract included realigning existing sewer infrastructure to Sydney Water's requirements.

The team also did the enabling works for future development of the former coke works site at Corrimal, near Wollongong. Construction took place from August 2024 to March 2025. Projects like this are part of our sewer construction services.

The confined site had strict controls on noise, lighting, sediment and heritage.

August 2024 – March 2025

The Challenge

Building within a protected environment

The site is next to a Grey-Headed Flying Fox camp. The species is vulnerable, so the team had to keep noise, lighting and activities near the habitat under tight control.

Excavation and earthworks meant a constant risk of sediment runoff, especially in wet weather. The site also has areas of Aboriginal cultural significance. An Aboriginal Heritage Impact Permit (AHIP) is the legal approval needed before any work that could harm Aboriginal objects or places. Work in those areas had to align with the permit.

Planning, stakeholder consultation and full compliance were part of the Corrimal Coke Works sewer job from day one.

The Solution

Risk management, compliance and collaboration

Risk management came first, with stakeholders involved on compliance from the start.

Sediment control. Silt fences and sediment basins protected nearby waterways and habitat.

Flying fox protection. The team adjusted work schedules and kept noise and lighting under control within 75m of the camp.

Cultural heritage. We worked with stakeholders to meet the AHIP conditions and protected the identified heritage areas during construction.

Live sewer connections. The crew made concurrent connections into the live sewer under Sydney Water's Flow Isolation and Flow Management (FIFM) requirements, with detailed FIFM planning behind them. At CH 520, a bypass diverted the existing flows while the new inlet was built into the manhole.

Project Outcome

Sewer delivered for future development of the site

RA Smith delivered the gravity sewer and its enabling works at the Corrimal Coke Works site.

Key Outcomes

  • 520m of DN450 gravity sewer delivered at an average depth of 6.5m
  • Manholes and sewer connections built
  • Concurrent connections made under Sydney Water FIFM, with a bypass at CH 520
  • Site preparation, access roads, fencing and amenities completed
  • Environmental risks managed throughout construction
  • Flying fox habitat protected by adjusting how and when the team worked
  • AHIP requirements met and cultural heritage areas protected

At Corrimal, RA Smith built the sewer and met its environmental and cultural heritage obligations on the same site. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.

Corrimal Coke Works Sewer Case Study

PDF · Full technical scope

Technical Scope

What the works involved

Enabling Works

  • Site clearing and grubbing
  • Bulk earthworks
  • Temporary access roads
  • Temporary fencing and site amenities
  • Potholing along the sewer alignment to get A-Class utility data and confirm the design connection locations

Gravity Sewer Works

  • 520m of DN450 polypropylene gravity sewer at an average depth of 6.5m
  • 218m of the pipe encased in concrete, just over 40 per cent of the line
  • Three DN1200 manholes and one DN1800 manhole
  • Concurrent sewer connections under Sydney Water's Flow Isolation and Flow Management (FIFM) requirements. At CH 00, a connection into the existing DN600 concrete sewer. At CH 520, a new inlet into the existing manhole, with a bypass diverting the flows.
  • Foundation, compaction, air, vacuum, CCTV and ovality testing to Sydney Water standards

FAQs

Corrimal Coke Works Sewer FAQs

What did RA Smith build at the Corrimal Coke Works site?

RA Smith installed 520m of DN450 polypropylene gravity sewer for Legacy Property, with three DN1200 manholes, one DN1800 manhole and the enabling works for future development of the site.

How deep is the Corrimal gravity sewer?

The pipe averages 6.5m deep, and 218m of it is encased in concrete.

What is FIFM on a Sydney Water sewer connection?

FIFM stands for Flow Isolation and Flow Management. At Corrimal, RA Smith made concurrent connections under these requirements and set up a bypass at CH 520 to divert the existing flows.

How did RA Smith protect the flying fox camp?

We adjusted work schedules and kept noise and lighting under control within 75m of the Grey-Headed Flying Fox camp.

What testing did the Corrimal sewer go through?

The sewer had foundation, compaction, air, vacuum, CCTV and ovality testing to Sydney Water standards.