

















Project Overview
RA Smith Contracting delivered the Moorebank Intermodal utilities for Georgiou across Stage 2 of the precinct in NSW. The work covered site-wide stormwater drainage, potable water, pressure sewer and fire hydrant services, plus conduits to each proposed warehouse.
The contract began at slightly less than $2 million for stormwater drainage and grew to $8 million as Georgiou awarded more work. Site work took place from January 2021 to July 2022. Work like this is part of our stormwater services and water construction services.
The Moorebank Intermodal Terminal Precinct has a rail shuttle link to Port Botany and more than 850,000 m2 of warehousing.
January 2021 – July 2022
The Challenge
Stage 2 needed several utility networks built at once across a developing industrial site. Much of the in-ground work fell in a period of extreme wet weather across the Sydney metropolitan region.
The first stormwater pipework discharges to on-site retention ponds. The ponds had not been built, so the pipework was capped. In the rain the system backed up and overflowed, and parts of the site flooded significantly.
The scope also kept growing. The contract began with stormwater drainage, and Georgiou added hydraulic services and further utility work as requirements changed. Resources, sequencing and delivery kept adjusting across several work fronts.
The Solution
We worked closely with Georgiou and the other stakeholders so each new stage of work fitted into the program as requirements changed.
Flood response. RA Smith worked with Georgiou to limit the effect of the flooding on the installed services and the wider site. The aim was to get every contractor on site back to work faster after heavy rain.
Staged delivery. Stormwater drainage went in from January to July 2021. The water, sewer and fire services followed from November 2021 to July 2022.
Scope growth and coordination. The team folded each addition into the program and coordinated with Georgiou and the other on-site contractors.
Project Outcome
RA Smith delivered the stormwater, potable water, pressure sewer and fire hydrant services for Stage 2. The contract grew from slightly under $2 million to $8 million.
On the Moorebank Intermodal utilities, Georgiou saw how RA Smith handled the initial scope and awarded significant additional work. The team stayed on site across the whole of Stage 2. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.
Moorebank Intermodal Freight Terminal Case Study
PDF · Full technical scope
Technical Scope
FAQs
RA Smith installed the primary stormwater network, potable water mains, pressure sewer and fire hydrant services across Stage 2 for Georgiou, plus conduits to each proposed warehouse.
About 5,400m of PE potable water main, 4,180m of pressure sewer and 2,600m of PE fire hydrant service, plus three sections of primary stormwater pipe from 375mm to 1650mm diameter.
The first stormwater pipework discharges to on-site retention ponds that had not been built, so it was capped. In extreme wet weather the system backed up and overflowed.
The trenches are 1.5m to 4.5m deep in the first section and 1.5m to 3.5m deep in the other two.
It started as a stormwater drainage contract of slightly less than $2 million. Georgiou awarded significant additional work after RA Smith performed the first scope, including hydraulic services and warehouse utility conduits.