/

/

ARTC Inland Rail

ARTC Inland Rail

Greg Fulmer

|

April 9, 2025

Client

ARTC

Location

Junee and Forbes, NSW

Value

$4.3 Million

Completed

September 2024

Construction workers and vehicles, including a white truck and excavator, are present at a work site near a railway track with safety barriers and equipment.Construction workers and vehicles, including a white truck and excavator, are present at a work site near a railway track with safety barriers and equipment.
A construction site with a large steel beam above a trench, a pipe laid on wooden supports, and safety barriers surrounding the area.A construction site with a large steel beam above a trench, a pipe laid on wooden supports, and safety barriers surrounding the area.
Two construction workers in safety gear work inside a reinforced excavation site with pipes, gravel, and equipment visible around them.Two construction workers in safety gear work inside a reinforced excavation site with pipes, gravel, and equipment visible around them.
Two trucks and workers are positioned near a roadside construction site beside a set of railway tracks, with houses and trees in the background under a partly cloudy sky.Two trucks and workers are positioned near a roadside construction site beside a set of railway tracks, with houses and trees in the background under a partly cloudy sky.
A construction site beside a railway features trucks, barriers, workers in safety gear, and construction equipment along a partially closed road.A construction site beside a railway features trucks, barriers, workers in safety gear, and construction equipment along a partially closed road.

Project Overview

Inland Rail utility relocations beneath live rail and a major highway

RA Smith Contracting delivered the Inland Rail utility relocations for ARTC at Junee and Forbes in NSW. RA Smith was Principal Contractor on the $4.3 million contract. The team diverted and realigned existing water, sewer and gas infrastructure so new rail assets could be built. 

Work included installation beneath a live rail corridor and across the Olympic Highway, from March 2023 to September 2024. Projects like this are part of our water construction services and sewer construction services. 

The relocations cleared the way for rail construction at Junee and Forbes, part of the wider Inland Rail program. 

March 2023 – September 2024

The Challenge

Delivering the Inland Rail utility relocations inside a live rail environment

The work meant installing water, sewer and gas infrastructure beneath a live rail corridor and across the Olympic Highway. Safe work with minimal disruption took careful planning and close coordination with multiple stakeholders. 

The Olympic Highway crossing was by open cut, which needed a full road closure and an approved traffic detour. The highway carries heavy vehicles, so the crossing needed extensive approvals and coordination with Council and the traffic authorities. 

Significant groundwater came in while the bore shafts were excavated. Commencement was also delayed, and the design went through multiple revisions before start. Both could affect sequencing and program on the Inland Rail utility relocations. 

The Solution

Methods matched to each constraint

Each constraint got its own method, and sequencing was reviewed as conditions changed. 

Groundwater control. Sediment tanks at the bore locations let pumping run continuously without slowing boring. Vacuum tankers took the extracted water to a licensed treatment facility, in line with environmental requirements. 

Olympic Highway crossing. We worked with Council and the traffic authorities to secure approvals. We then installed 62m of DN375 DICL water main by open cut under the closure and detour, with full pavement reinstatement. 

Live rail interface. The crew bored the 88m DN375 MSCL water main inside a DN600 steel casing with a minimum 2.5m cover. They also completed an 82m gas bore beneath the railway corridor. 

Design and program changes. RA Smith reviewed methods and sequencing as design revisions, groundwater and stakeholder requirements changed, which kept the work moving.

Project Outcome

Utility relocations delivered beneath live rail and across a major highway

RA Smith completed the potable water, gravity sewer and gas relocations despite delayed commencement and design revisions before start.

Key Outcomes

  • Water, sewer and gas relocations delivered at Junee and Forbes 
  • 88m DN375 MSCL water main bored beneath the live rail corridor 
  • 62m DN375 DICL water main installed across the Olympic Highway, with full pavement reinstatement 
  • 45m DN225 PVC sewer microtunnelled beneath existing infrastructure 
  • 82m gas bore completed beneath the railway corridor 
  • Groundwater managed through dewatering, with boring productivity maintained 
  • Approvals coordinated with Council and traffic authorities for the highway closure and detour 

RA Smith delivered the Inland Rail utility relocations safely and in line with ARTC's project objectives. The highway crossing went ahead under a full closure. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.

ARTC Inland Rail Case Study

PDF · Full technical scope

Technical Scope

What the works involved

Potable Water Main

  • 88m of DN375 MSCL water main in a DN600 steel casing, bored beneath the live rail corridor with a minimum 2.5m cover 
  • 4.5m deep launch shaft in the rail reserve and 3.5m deep receive shaft in Railway Parade 
  • Final tie-ins to approved design drawings 
  • 62m of DN375 DICL water main by open cut across the Olympic Highway, with full pavement reinstatement and tie-ins to existing infrastructure 
  • Grout filling and abandonment in place of the existing DN375 GWCC water main 
  • 110m of DN150 DICL water main along the southern side of Railway Parade and the western side of the railway corridor 

Sewer Main

  • 45m of DN225 PVC gravity sewer by DN425 microtunnelling beneath existing infrastructure 
  • 4.5m deep launch shaft and 2.5m deep receive shaft 
  • Two new maintenance structures 
  • 10m of DN225 PVC sewer by open cut, with two new maintenance structures over the existing sewer alignment

Gas

  • Launch and receive shafts and an 82m bore beneath the railway corridor 
  • DN250 PE sleeve installed to utility authority requirements 

FAQs

ARTC Inland Rail FAQs

What did RA Smith build for ARTC Inland Rail at Junee and Forbes?

RA Smith relocated potable water, gravity sewer and gas infrastructure for ARTC as Principal Contractor, including an 88m DN375 MSCL water main bored beneath a live rail corridor, 45m of DN225 PVC sewer by microtunnelling and an 82m gas bore.

How did RA Smith manage groundwater at the bore shafts?

Sediment tanks at the bore locations let pumping continue without slowing boring, and vacuum tankers took the extracted water to a licensed treatment facility.

How was the Olympic Highway crossing built?

RA Smith installed 62m of DN375 DICL water main by open cut across the highway under a full road closure and an approved traffic detour. RA Smith secured approvals from Council and the traffic authorities first, then reinstated the pavement in full.

How deep were the launch and receive shafts?

The water main bore used a 4.5m deep launch shaft and a 3.5m deep receive shaft. The sewer microtunnel used a 4.5m deep launch shaft and a 2.5m deep receive shaft.

How much cover does the water main have under the railway?

The 88m DN375 MSCL water main was bored inside a DN600 steel casing with a minimum 2.5m cover beneath the live rail corridor.

Our Projects