





















Project Overview
RA Smith Contracting built stormwater drainage and a discharge structure on the Sydney Gateway stormwater works at St Peters and Mascot. The client was the JHSW JV (John Holland and Seymour Whyte), and the $4.1 million package ran from January 2022 to March 2023.
The work included a sheet-pile coffer dam in Alexandra Canal and twin DN1500 RCP outlet pipes. It also covered 390m of carrier trench in water-charged ground and twin DN1800 RCP pipes beneath an operational rail siding. Stormwater work like this is part of our stormwater services.
Most of the work was in wet ground, with parts in a waterway and under rail.
January 2022 to March 2023
The Challenge
The ground was water-charged, and some of it had been pre-stabilised while some had not. Groundwater management was essential, and the excavations were inherently unstable for the people working in them.
The outlet had to go into Alexandra Canal, a tributary of the Cooks River. That meant working inside a coffer dam, with sediment controls to hold back any discharge of material.
The twin DN1800 pipes beneath the rail line were planned for a 7-day possession that started at 7:00am on Christmas Day. The work was time-critical, and the detailed planning involved the other contractors.
The Solution
RA Smith used a different method for each condition and planned the possession work in detail.
Canal outlet. The crew installed a steel sheet-pile coffer dam in the canal and put sediment controls beyond the piles. A spear-type dewatering system managed inflows through the sheet piles. The crew then prepared the canal bed foundation, laid the twin DN1500 RCP pipes and backfilled. Basalt spalls from 100mm to 300mm went in below water level to protect the canal from erosion by the new discharge.
Carrier trench. The crew used two 4m long by 2.4m high shore boxes, to a full depth of about 3m. TS60 geotextile and basalt spalls formed a bedding mattress that funnelled groundwater beneath the pipe. Two 4 inch trailer-mounted pumps held the water table down after two significant rain events.
Embedment. The crew compacted 14mm aggregate below and around the pipe, which was wrapped in TS60 geotextile. They then placed and compacted 20mm sandstone backfill over it.
Rail crossing. Resources were mobilised for the possession window, with the work planned alongside the other contractors.
Project Outcome
RA Smith delivered the Sydney Gateway stormwater packages without incident or delay.
The experience from earlier works on the project helped manage the groundwater and the unstable ground. RA Smith has worked on several Sydney Gateway contracts and still provides enabling works there. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.
Technical Scope
FAQs
RA Smith installed primary stormwater drainage and a discharge structure for the JHSW JV, including twin DN1500 RCP outlet pipes in Alexandra Canal, about 390m of carrier trench in water-charged ground and twin DN1800 RCP pipes beneath an operational rail siding.
RA Smith installed a steel sheet-pile coffer dam in the canal, with sediment controls beyond the piles and a spear-type dewatering system to manage inflows. The crew then prepared the canal bed, laid the twin DN1500 RCP pipes, backfilled and placed 100mm to 300mm basalt spalls below water level for erosion protection.
RA Smith used two 4m long by 2.4m high shore boxes for support, laid TS60 geotextile and basalt spalls as a bedding mattress to funnel groundwater beneath the pipe, and ran two 4 inch trailer-mounted pumps after two significant rain events.
The work was planned for a 7-day rail possession starting at 7:00am on Christmas Day. RA Smith planned it in detail with the other contractors, because the work was time-critical.
The carrier has 356m of twin DN1500 RCP, 6m of single DN1350 RCP and 28m of single DN1200 RCP, with a 0.2% grade, across about 390m of excavation.