Cabramatta Loop Sewer Diversion

Cabramatta Loop Sewer Diversion

Web Developer

|

November 26, 2026

Client

Fulton Hogan

Location

Cabramatta, NSW

Value

$1.8 million

Completed

July 2023

Sewer diversion by RA Smith at CabramattaSewer diversion by RA Smith at Cabramatta
Excavating on the Cabramatta Sewer Diversion ProjectExcavating on the Cabramatta Sewer Diversion Project

Project Overview

Cabramatta Loop sewer diversion for the ARTC rail upgrade.

RA Smith Contracting delivered the Cabramatta Loop sewer diversion for Fulton Hogan on the ARTC Cabramatta Loop Project. The team realigned a gravity sewer carrier and a pressure main to make room for new rail infrastructure. RA Smith also handled all the Sydney Water works on the $1.8 million job. 

Site work took place from November 2022 to July 2023. The job included 320m of DN450 gravity sewer and 520m of DN375 pressure main. Sewer diversions like this are part of our sewer construction services. 

ARTC's Cabramatta Loop lets freight trains pass each other on the Southern Sydney Freight Line. 

November 2022 to July 2023

The Challenge

Unrecorded concrete, weak foundations and live connections

The diversion tied into live Sydney Water sewers. Every connection ran under Sydney Water's Flow Isolation and Flow Management (FIFM) procedures. At CH 00 and CH 320 the team found concrete foundations supporting the 375 and 400 VC mains. 

An unexpected challenge arose on the pressure main. The DN375 CICL main was concrete encased at the CH 00 connection point. The design documents did not show it. During the FIFM isolation, the main also could not be drained or scoured for the connection. 

At CH 13 the foundation layer did not meet Sydney Water requirements. The ground along the gravity sewer was water charged. Commencement was delayed, and the design changed several times before start. 

The Solution

Approved methods for each unforeseen condition

Each problem got its own method, proposed to Fulton Hogan or Sydney Water. Sequencing changed as conditions did. 

Live gravity connections. At CH 00 and CH 320 the crew removed the concrete foundations. They fitted DN300 and DN375 GRP rocker pipes to the mains, so two DN1200 manholes could go over them. A bypass diverted the flows during the FIFM connections. The method changed on the day, and the work finished over two consecutive days. 

Foundation remediation. RA Smith worked with its geotechnical engineer on a remediation procedure that was constructable and cost effective. The team laid the DN450 PP pipe on treated foundation from CH 13 to CH 150, including the three DN1200 manholes. 

Encasement removal. RA Smith proposed a removal method to Sydney Water. Sydney Water allowed the work during its trial isolation of the pump station and the DN375 main. The crew removed 5m of encasement by hand and kept the main intact. 

Draining the main. The isolation showed the main could not be drained or scoured. An approved Sydney Water contractor fitted a 375 x 100 hot tap. RA Smith installed a scour line into the gravity manhole. 

Project Outcome

Sewer diversions delivered, with the pressure main ahead of schedule

RA Smith completed the gravity and pressure sewer diversions despite extended commencement delays and multiple design changes before start.

Key Outcomes

  • 320m of DN450 polypropylene gravity sewer installed at an average depth of 4.5m in water charged ground 
  • Three DN1200 manholes built 
  • Concurrent connections made at CH 00 and CH 320 under FIFM, with a bypass diverting existing flows 
  • Foundation remediated where it did not meet Sydney Water requirements 
  • 520m of DN375 CICL and DICL pressure main installed at an average depth of 1.5m 
  • 5m of concrete encasement removed by hand while keeping the existing main intact 
  • Pressure main completed ahead of schedule after the gravity main

On the Cabramatta Loop sewer diversion, RA Smith worked out a method for each issue as it came up on site. The pressure main went in ahead of schedule once the gravity main was done. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.

Technical Scope

What the works involved

Gravity Sewer Works

  • Potholing along the alignment to get A-Class data and confirm the design connection locations 
  • Upfront Sydney Water connection under a FIFM bypass, with DN300 and DN375 GRP rocker pipes fitted to the existing mains for two DN1200 DTC manholes at CH 00 and CH 320 
  • 320m of DN450 PP pipe excavated, laid and backfilled at an average depth of 4.5m in water charged ground 
  • 150m of foundation remediated where it did not meet the design requirements 
  • Three DN1200 manholes 
  • Concurrent sewer connections at CH 00 and CH 320 under FIFM, with a bypass diverting existing flows 
  • Foundation, compaction, air, vacuum, CCTV and ovality testing to Sydney Water standards 

Pressure Sewer Works

  • Potholing along the alignment to get A-Class data and confirm the design connection locations 
  • 520m of DN375 CICL and DICL pipe excavated, laid and backfilled at an average depth of 1.5m 
  • Concrete encasement to protect the new main near existing services 
  • Hydrostatic pressure testing and compaction testing 
  • 375 x 100 hot tap, fitted by an approved Sydney Water contractor so the existing main could be drained for the connection 
  • Scour line installed into the existing sewer manhole 
  • 5m of existing concrete encasement removed during Sydney Water's trial isolation, to allow the connection 
  • DN375 Sydney Water pressure sewer connection completed under pump station isolation in a rail corridor

FAQs

Cabramatta Loop Sewer Diversion FAQs

What did RA Smith build on the Cabramatta Loop?

RA Smith realigned an existing gravity sewer carrier and pressure main for Fulton Hogan on the ARTC Cabramatta Loop Project, installing 320m of DN450 gravity sewer and 520m of DN375 pressure main.

What concrete did RA Smith find on the Cabramatta pressure main?

The existing DN375 CICL main was concrete encased at the CH 00 connection point, and the design documents did not show it. RA Smith proposed a removal method to Sydney Water, then removed 5m of encasement by hand during a trial isolation.

Why did the Cabramatta pressure main need a hot tap?

The existing main could not be drained or scoured during the FIFM isolation, so an approved Sydney Water contractor installed a 375 x 100 hot tap. RA Smith added a scour line into the existing gravity manhole.

How was the poor foundation fixed on the Cabramatta gravity sewer?

The existing foundation at CH 13 did not meet Sydney Water requirements. RA Smith and its geotechnical engineer proposed a remediation procedure to Fulton Hogan, and the DN450 PP pipe went in with foundation treatment from CH 13 to CH 150.

How were the live sewer connections made under FIFM?

At CH 00 and CH 320, RA Smith installed DN300 and DN375 GRP rocker pipes on the existing mains under a Sydney Water FIFM bypass, built two DN1200 manholes over them and made concurrent connections while the bypass diverted existing flows.