Northern Village Distribution Watermain

Northern Village Distribution Watermain

Web Developer

|

November 26, 2026

Client

Wingecarribee Shire Council

Location

Willow Vale, NSW

Value

$1.8 million

Completed

July 2025

northern-village-watermain-projectnorthern-village-watermain-project
northern-village-watermain-drillnorthern-village-watermain-drill
northern-village-watermain-project(2)northern-village-watermain-project(2)
northern-village-watermainnorthern-village-watermain

Project Overview

Northern Village watermain, 900m of DN450 DICL along an existing road

RA Smith Contracting installed the Northern Village watermain for Wingecarribee Shire Council. The team laid 900m of DN450 DICL watermain along an existing road at Willow Vale, NSW, on a $1.8 million job. 

Site work ran from March 2025 to July 2025. The team also connected into the existing DN300 and DN500 watermains. Watermain work like this is part of our water construction services. 

Each day's trench had to be backfilled by the end of the shift, so the road stayed workable.

March 2025 to July 2025

The Challenge

Rock in the trench line and a live road to keep working

The alignment ran along an existing road. Each section of trench laid during the day had to be backfilled before the crew left. 

Rock turned up along the trench line. It was hard to remove and slowed progress, even with excavator-mounted hydraulic hammers. 

The route crossed a high pressure gas main and the road. The DN300 connection needed a temporary road around it. Existing services crossing the road had to be located first.

The Solution

A second excavator ahead of the pipe layers

The crew started by potholing every existing service crossing the road. They then worked section by section, backfilling each shift's trench. 

Rock. The management team put a second excavator on site to pre-break the rock ahead of the pipe-laying crew. Productivity improved significantly. 

Gas crossing. We crossed the high pressure gas main and the road as part of the main alignment. 

Connections. A temporary road went in around the DN300 connection. The team then connected into the existing DN300 and DN500 mains. 

Project Outcome

900m of watermain delivered on schedule with no incidents

RA Smith delivered the 900m DN450 DICL watermain without incidents or environmental issues, within the approved construction schedule.

Key Outcomes

  • 900m of DN450 DICL watermain installed along an existing road 
  • Connections made into the existing DN300 and DN500 watermains 
  • Works completed within the approved construction schedule 
  • No incidents or environmental issues 
  • All connections made within the planned timeframes

The connections went in within the planned timeframes, which kept the existing network operating and the project milestones on track. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.

Technical Scope

What the works involved

Watermain Works

  • Site compound set up 
  • Potholing of all existing services crossing the road 
  • Crossing of a high pressure gas main and the road 
  • 900m of DN450 DICL watermain 
  • Temporary road around the DN300 connection 
  • Connections into the existing DN300 and DN500 watermains 

FAQs

Northern Village Distribution Watermain FAQs

What did RA Smith build on the Northern Village watermain?

RA Smith installed 900m of DN450 DICL watermain along an existing road for Wingecarribee Shire Council, and connected it into the existing DN300 and DN500 mains.

What slowed the Northern Village watermain trenching?

Rock along the trench line was hard to remove and slowed progress, even with excavator-mounted hydraulic hammers.

How did RA Smith keep the Northern Village watermain on schedule?

RA Smith deployed an additional excavator to pre-break the rock ahead of the pipe-laying crew, which improved productivity significantly.

Was the trench left open overnight on the Northern Village watermain?

No. Each section installed during the day was backfilled by the end of the shift.

What did the Northern Village watermain connect into?

The new DN450 DICL main connects into an existing DN300 watermain and an existing DN500 watermain.