Project Overview
RA Smith Contracting completed the Gardeners Road sewer replacement at Mascot for the CPB Dragados Samsung JV on WestConnex. The $2 million contract ran from January to October 2020.
The client first awarded RA Smith line 2 and, once it was complete, instructed the team to finish lines 1 and 3. Line 2 was 170m of concrete-encased DN225 sewer, 2m to 3m deep, and all of it was night work. Lines 1 and 3 added 155m at 1.5m to 2.2m deep. A further 38m of DN225 at 4m deep included a 32m, 425mm horizontal bore under Bourke Road. Sewer work like this is part of our sewer construction services.
Most of it was inwater-charged ground in front of factories that needed 24 hour access.
January 2020 to October 2020
The Challenge
The ground on Gardeners Road was water-charged and ran as sand. Dewatering spears couldn't hold the water level down, because marine mud sat just below excavation level.
Foundation bearing capacity didn't reach 100kPa. The road also had to open each day, so all dewatering had to be buried below the road surface. Factories along the road needed access around the clock.
Each stage of the exhume, replace and encase sequence had to be decommissioned each night. Property connections had to be intercepted as the work moved along.
The Solution
RA Smith adapted the dewatering and foundation methods to the ground and sequenced the sewer in nightly stages.
Dewatering. The team buried spear dewatering below the road surface so traffic could use the road during the day. Where the spears couldn't hold the level against running sand and marine mud, the crew added sump pumping.
Foundation. Where bearing capacity fell short of 100kPa, the crew laid 450mm of ballast wrapped in geofabric.
Staged replacement. RA Smith exhumed the existing sewer, replaced it and encased it in stages. The crew decommissioned each stage at night and intercepted property connections as the work progressed.
Bourke Road bore. For the 38m run at 4m deep, the crew drilled a 32m, 425mm horizontal bore under Bourke Road. The bore reached an existing sewer in the centre median, where the new line intercepted it.
Maintenance structures. The team built three 1200mm diameter maintenance structures and five maintenance shafts. It also demolished three existing maintenance structures.
Project Outcome
RA Smith replaced 325m of DN225 sewer on Gardeners Road and built a further 38m beneath Bourke Road through a 32m bore.
RA Smith also won ITS work on Gardeners Road, all at night, plus additional sewer and water work. Our Integrated Management System is third party accredited to AS/NZS ISO 9001:2015, ISO 45001:2018 and ISO 14001:2015.
Technical Scope
FAQs
RA Smith replaced 325m of DN225 sewer on Gardeners Road, Mascot, for the CPB Dragados Samsung JV. It also built 38m of DN225 at 4m deep through a 32m, 425mm horizontal bore under Bourke Road, and constructed three maintenance structures and five maintenance shafts.
The ground was water-charged running sand, with marine mud just below excavation level. RA Smith used dewatering spears buried below the road surface and added sump pumping where the spears couldn't hold the water level down.
The crew drilled a 32m, 425mm horizontal bore under Bourke Road. It reached an existing sewer in the centre median, where the new 38m run at 4m deep intercepted it.
All dewatering was buried below the road surface. RA Smith replaced the sewer in stages and decommissioned each stage at night, intercepting property connections as the work progressed.
Line 2 is 2m to 3m deep. Lines 1 and 3 are 1.5m to 2.2m deep. The run that crosses under Bourke Road is 4m deep.