Water Infrastructure

The Northern Road – Stage 3

Client

Lendlease Engineering

Location

Western Sydney

Value

$6.9 Million

Completed

October 2021

A large excavator positions a pipe above a fenced-off deep excavation site while a worker in safety gear observes nearby on a sunny day.A large excavator positions a pipe above a fenced-off deep excavation site while a worker in safety gear observes nearby on a sunny day.
A construction site with workers and excavators digging a trench along a roadside, surrounded by equipment, pipes, and safety barriers.A construction site with workers and excavators digging a trench along a roadside, surrounded by equipment, pipes, and safety barriers.
A small excavator is digging a trench in a residential area, exposing pipes and cables, with safety barriers and traffic cones set up nearby.A small excavator is digging a trench in a residential area, exposing pipes and cables, with safety barriers and traffic cones set up nearby.
A construction worker in a high-visibility jacket and helmet installs steel reinforcement bars over a black membrane inside a trench on a worksite.A construction worker in a high-visibility jacket and helmet installs steel reinforcement bars over a black membrane inside a trench on a worksite.
RA Smith successfully relocated Sydney Water infrastructure, addressing complex trenching challenges with precision and efficiency.

Pipe Installation:

6.4km of DN600 and DN150/DN100 mains.

Testing & Compliance:

All pipelines met required standards.

Timely Delivery:

Completed ahead of schedule.