Sewer Infrastructure






Pipeline Installation:
Excavate, lay, and backfill 520m of DN450 PP pipe, including 218m of concrete encasement, at an average depth of 6.5m.Sewer Installation:
25 main adjustments and MH rebuilds, 4m–7m deep.MH Construction:
Construct 3 x DN1200 and 1 x DN1800 manholes.Detailed FIFM Planning:
Undertake concurrent sewer connections at CH 00 into the existing DN600 concrete sewer and at CH 520, constructing a new inlet into the existing MH while under Sydney Water FIFM, with a bypass set up to divert existing flows.